HomeLatestMumbai RERA Orders Ghatkopar Builder Refund Rs 189 Crore Buyers

Mumbai RERA Orders Ghatkopar Builder Refund Rs 189 Crore Buyers

In a decisive enforcement of homebuyers’ rights, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has directed a Ghatkopar-based developer to refund ₹1.89 crore, along with interest, to two flat buyers for delayed possession of apartments in the North Sea Heights project.

The ruling reflects the authority’s commitment to protecting citizens against prolonged project delays and upholding transparency in real estate transactions.According to official statements, the buyers had booked flats in 2012 and paid a cumulative ₹1.89 crore by 2018. The developer had promised possession by December 31, 2018, but construction stalled, leaving municipal approvals incomplete and the flats undelivered. Frustrated, the buyers approached MahaRERA seeking a full refund with statutory interest as mandated under Section 18 of the Real Estate (Regulation and Development) Act, 2016.

Also Watch: An Exclusive Interview with Sanjeev Jaiswal (IAS), CEO MHADA

The authority ruled that the developer’s defence, citing arbitration clauses, delayed payments by other allottees, and financial stress, lacked legal merit. Officials observed that even by the extended possession deadlines, construction was incomplete, demonstrating a clear violation of statutory obligations. MahaRERA instructed the developer to pay interest calculated at the highest Marginal Cost Lending Rate (MCLR) of the State Bank of India plus 2% from the date of payment until full refund.

Experts note that this decision is a landmark for homebuyers in Maharashtra, sending a strong message to developers about adherence to delivery timelines. “The ruling reinforces the need for accountability in real estate projects and ensures buyers’ investments are protected,” an official from MahaRERA said.The case highlights broader concerns in Mumbai’s real estate sector, where delayed projects often leave citizens financially and emotionally strained. Analysts suggest that stricter enforcement of RERA regulations and transparent communication by builders can prevent similar disputes, fostering a more equitable and reliable housing ecosystem.

Furthermore, the verdict underscores the importance of government agencies in maintaining trust between developers and consumers. By enforcing timely refunds with interest, authorities aim to balance commercial interests with citizen rights, ensuring that urban growth aligns with principles of fairness and accountability.For Mumbai residents, the ruling represents both relief and reassurance that legal mechanisms exist to address developer negligence. It also sets a precedent for other flat buyers across the state, reinforcing the notion that regulatory oversight can enforce timely compliance and financial justice in India’s booming property market.The decision by MahaRERA not only safeguards the interests of individual homebuyers but also strengthens confidence in regulated real estate practices, promoting transparency and equity in urban housing development across Maharashtra.

Also Read : Mumbai To Host Rs 30000 Crore Green Data Centre Park
Mumbai RERA Orders Ghatkopar Builder Refund Rs 189 Crore Buyers
RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -spot_img

Most Popular

Recent Comments

Goldmedal Launches Energy Efficient Spacio Ceiling Fan

Goldmedal Launches Energy Efficient Spacio Ceiling Fan

0
Goldmedal Electricals has unveiled its latest energy-efficient offering, the Spacio BLDC Ceiling Fan, targeting urban households and commercial spaces seeking lower energy consumption without...
Vedhee Kapoor Joins Runwal Realty Mumbai Luxury

Vedhee Kapoor Joins Runwal Realty Mumbai Luxury

0
Runwal Realty has reinforced its leadership in Mumbai’s luxury residential segment with the appointment of Vedhee Kapoor as Cluster Head – Mumbai Luxury. The...
Shapoorji Pallonji Introduces Heartland Project In Mulund

Shapoorji Pallonji Introduces Heartland Project In Mulund

0
Mumbai’s Mulund neighbourhood has witnessed the launch of a new residential project, signalling continued investor confidence in the micro-market and the evolving preferences of...
Ashar Group Completes Luxury Project In Mumbai

Ashar Group Completes Luxury Project In Mumbai

0
A landmark redevelopment project in Mumbai’s Pali Hill has received its Occupation Certificate, marking the completion of a high-profile luxury housing initiative on the...
SRA Examines Complaints On Re-Erected Huts In Dharavi Redevelopment

SRA Examines Complaints On Re-Erected Huts In Dharavi Redevelopment

0
Mumbai’s largest urban renewal exercise has come under renewed scrutiny after authorities initiated an official inquiry into allegations of irregular beneficiary inclusion within the...